Freeway Closures Schedule for I-10 HOV Project

Check the schedule of Freeway closures.

The California Department of Transportation (Caltrans) will close portions of the San Bernardino Freeway (I-10) as part of the High Occupancy Vehicle lane construction project. The following schedule will be in effect, weather permitting:

Continuing Long Term Closures
Bess Avenue Pedestrian Overcrossing
Full closure of Bess Avenue pedestrian overcrossing through fall, 2012

Eastbound I-10
Baldwin Park Boulevard on-ramp through December, 2012
                                                                               
Westbound I-10
Baldwin Park Boulevard on- and off-ramps through December, 2012

Sunday, December 2
·        11:59 p.m. to 6 a.m. – Southbound I-605 connector to eastbound I-10.
·        11:59 p.m. to 6 a.m. – Northbound I-605 connectors to I-10.
·        11:59 p.m. to 5 a.m. – Northbound I-605 Valley Boulevard on-ramps.

Westbound I-10
·        11:59 p.m. to 5 a.m. – Up to 3 lanes from Puente Avenue to I-605.
·        11:59 p.m. to 4 a.m. – Full freeway closure from Puente Avenue to I-605.
·        11:59 p.m. to 5 a.m. – Connector to I-605.
·        11:59 p.m. to 6 a.m. – Frazier Street, Baldwin Park Boulevard and Francisquito Avenue on- and off-ramps.
·        11:59 p.m. to 6 a.m. – Puente Avenue on-ramp.

Eastbound I-10
·        11:59 p.m. to 6 a.m. – Up to 3 lanes from I-605 to Puente Avenue.
·        11:59 p.m. to 5 a.m. – Full freeway closure from I-605 to Puente Avenue.
·        11:59 p.m. to 6 a.m. – Connector to northbound I-605.
·        11:59 p.m. to 6 a.m. – Durfee Avenue on-ramp.
·        11:59 p.m. to 7 a.m. – Frazier Street off-ramp.  
·        11:59 p.m. to 6 a.m. – Baldwin Park Boulevard on- and off-ramps.
·        11:59 p.m. to 6 a.m. – Francisquito Avenue off-ramp.

Monday, December 3 through Thursday, December 6
·        8 p.m. to 6 a.m. – Southbound I-605 connector to eastbound I-10.
·        7 p.m. to 6 a.m. – Northbound I-605 connectors to I-10.
·        8 p.m. to 5 a.m. – Northbound I-605 Valley Boulevard on-ramps.

Westbound I-10
·        9 a.m. to 3 p.m. - Frazier Street. Baldwin Park Boulevard and Francisquito Avenue on- and off-ramps.
·        9 p.m. to 5 a.m. – Up to 3 lanes from Puente Avenue to I-605.
·        11 p.m. to 4 a.m. – Full freeway closure from Puente Avenue to I-605.
·        9 p.m. to 5 a.m. – Connector to I-605.
·        7 p.m. to 6 a.m. – Frazier Street, Baldwin Park Boulevard, and Francisquito Avenue on- and off-ramps.
·        9 p.m. to 6 a.m. – Puente Avenue on-ramp.

Eastbound I-10        
·        9 a.m. to 3 p.m. – Baldwin Park Boulevard on- and off-ramps.
·        10 p.m. to 6 a.m. – Up to 3 lanes from I-605 to Puente Avenue.
·        1 a.m. to 5 a.m. - Full freeway closure from I-605 to Puente Avenue.
·        9 p.m. to 6 a.m. – Connector to northbound I-605.

Follow Baldwin Park Patch on Twitter, "Like" us on Facebook, or sign up for our newsletter.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here

More from Baldwin Park