Freeway Closures Scheduled for I-10 in Baldwin Park

The following schedule include a 55 hour closure of three I-605 and I-10 connectors.

The California Department of Transportation (Caltrans) will close portions of the San Bernardino Freeway (I-10) as part of the High Occupancy Vehicle lane construction project.

The following schedule will be in effect, weather permitting , and is subject to change:

Continuing Long Term Closure

Bess Avenue Pedestrian Overcrossing

Full closure of Bess Avenue pedestrian overcrossing through spring, 2013
                                                                                                                                         

Extended 55 Hour Closure

  • 10 p.m. Friday, April 19 through 5 a.m. Monday, April 22
  • Valley Boulevard on-ramp to northbound I-605
  • Northbound I-605 connector to westbound I-10
  • Southbound I-605 connector to eastbound I-10
  • Eastbound I-10 connector to northbound I-605


Friday, April 19

Westbound I-10

·         10 p.m. to 7 a.m. – Up to 4 lanes from Puente Avenue to I-605.

·         7 p.m. to 10 a.m. – Frazier Street, Baldwin Park Boulevard, and Francisquito Avenue on- and off-ramps.

·         9 p.m. to 9 a.m. – Puente Avenue on-ramp.

 
Eastbound I-10

·         11 p.m. to 8 a.m. – Up to 3 lanes from I-605 to Puente Avenue.

·         10 p.m. to 9 a.m. – Durfee Avenue on-ramp.

·         9 p.m. to 11 a.m. – Frazier Street off-ramp.

·         7 p.m. to 10 a.m. – Baldwin Park Boulevard on- and off-ramps.

·         11 p.m. to 10 a.m. – Francisquito Avenue off-ramp



Saturday, April 20

Westbound I-10

·         11 p.m. to 9 a.m. – Up to 3 lanes from Puente Avenue to I-605.

·         1 a.m. to 6 a.m. – Full freeway closure from Puente Avenue to I-605.

·         3 p.m. to 11 a.m. – Frazier Street and Francisquito Avenue on- and off-ramps.

·         11 p.m. to 11 a.m. – Francisquito Avenue on-ramp.

·         8 p.m. to 11 a.m. – Puente Avenue on-ramp.

                     

Eastbound I-10

·         11 p.m. to 10 a.m. – Up to 3 lanes from I-605 to Puente Avenue.

·         2 a.m. to 7 a.m. – Full freeway closure from I-605 to Puente Avenue.

·         9 p.m. to 10 a.m. – Durfee Avenue on-ramp.

·         3 p.m. to 11 a.m. – Baldwin Park Boulevard on- and off-ramps.

·         11:59 p.m. to 11 a.m. – Francisquito Avenue off-ramp

 

Sunday, April 21

Westbound I-10

·         10 p.m. to 5 a.m. – Up to 3 lanes from Puente Avenue to I-605.

·         11:59 p.m. to 4 a.m. – Full freeway closure from Puente Avenue to I-605.

·         9 p.m. to 5 a.m. – Connector to I-605.

·         3 p.m. to 6 a.m. – Frazier Street and Francisquito Avenue on- and off-ramps.

·         8 p.m. to 6 a.m. – Puente Avenue on-ramp.

 

Eastbound I-10

·         10 p.m. to 6 a.m. – Up to 3 lanes from I-605 to Puente Avenue.

·         1 a.m. to 5 a.m. – Full freeway closure from I-605 to Puente Avenue.

·         9 p.m. to 6 a.m. – Durfee Avenue on-ramp.

·         7 p.m. to 7 a.m. – Frazier Street off-ramp.

·         3 p.m. to 6 a.m. – Baldwin Park Boulevard on- and off-ramps.

·         10 p.m. to 6 a.m. – Francisquito Avenue off-ramp.

                                     

Monday, April 22 through Thursday, April 25

·         8 p.m. to 6 a.m. – Southbound I-605 connector to eastbound I-10.

·         7 p.m. to 6 a.m. – Northbound I-605 connectors to I-10.

·         8 p.m. to 5 a.m. – Northbound I-605 Valley Boulevard on-ramps.

 

Westbound I-10

·         9 a.m. to 3 p.m. - Frazier Street. Baldwin Park Boulevard and Francisquito Avenue on- and off-ramps.

·         9 p.m. to 5 a.m. – Up to 3 lanes from Puente Avenue to I-605.

·         11 p.m. to 4 a.m. – Full freeway closure from Puente Avenue to I-605.

·         9 p.m. to 5 a.m. – Connector to I-605.

·         7 p.m. to 6 a.m. – Frazier Street, Baldwin Park Boulevard, and Francisquito Avenue on- and off-ramps.

·         9 p.m. to 6 a.m. – Puente Avenue on-ramp.

 
Eastbound I-10                                                                                                                             

·         9 a.m. to 3 p.m. – Baldwin Park Boulevard on- and off-ramps.

·         10 p.m. to 6 a.m. – Up to 3 lanes from I-605 to Puente Avenue.

·         1 a.m. to 5 a.m. - Full freeway closure from I-605 to Puente Avenue.

·         9 p.m. to 6 a.m. – Connector to northbound I-605.

·         9 p.m. to 6 a.m. – Durfee Avenue on-ramp.

·         8 p.m. to 7 a.m. – Frazier Street off-ramp.

·         7 p.m. to 6 a.m. – Baldwin Park Boulevard on- and off-ramps.

·         10 p.m. to 6 a.m. – Francisquito Avenue off-ramp.

Find out what's happening in Baldwin Parkwith free, real-time updates from Patch.

- California Department of Transportation